OEE: availability, performance, quality
The three losses OEE decomposes — and how production runs feed each factor.
OEE answers one question: of the time a line or asset was scheduled to run, how much produced good output at full speed? It decomposes into three factors — availability (was it running), performance (at what speed), quality (good output or scrap).
- The three factors
- Availability — run time vs planned time; losses are stops and breakdowns.
- Performance — actual rate vs ideal rate; losses are slow cycles and minor stops.
- Quality — good units vs total; losses are rejects and rework.
Production runs in OEE capture the counts and timings each factor needs — planned time, downtime, output totals and rejects. The score is only as honest as the run logging; an unlogged stop is invisible loss.
- Where the data comes from
OEE 85% is world-class lore, not a universal target — a single-factor line at 60% might be excellent. Watch the factor that's lowest; it tells you which loss to attack first.
- Read it honestly